Route 2
ROUTE 2 (10.5KMS) :
Muff village to Derry via border crossing
The Stage 1 scheme assessment report for route 2 appraising route corridor options was published on 23 May 2018. Public consultation days were held for route 2 on 23 and 24 May 2018 with over 300 members of the public attending (combined).
In November 2018, the emerging preferred route linking Derry to Muff via Culmore was made available to the general public in the Stage 2 Preferred Route Corridor Selection Report for route 2.
Public information events were held on 28 and 29 November in Culmore and Muff respectively.
Subsequently, both Councils commenced the planning process for the preferred route in their respective jurisdiction. Construction is scheduled to commence before January 2020.