Works have been continuing in Brooke Park across all the buildings, the MUGA and the landscaped areas. At the bottom of the Park, the gate lodge has had a dehumidifier and blow heater installed at various intervals throughout the month. The electricians and plumbers have continued to work on the horticultural training centre and the contact sports centre. Work has also been continuing on the roof of the Café/pavilion. The rubber fill has been laid onto the MUGA and the stone mason has been busy with the boundary walls and pillars at Rosemount Avenue. The top soil has been laid out on some of the proposed new beds and the area forming the new playground and terrace has been marked out and excavated.
Block Work & Mechanical Ventilation System in Sports Centre
Blow Heater in Gate Lodge
Completed MUGA Carpet with Sand & Rubber
Electrics in HTC
External Door Frame in Contact Sports Centre
Inside Proposed Cafe / Pavilion
Laying Terrace between Cafe and Childrens Playground
Middle Top Stone Steps between Pond and Cafe
New Stone Pillar at Rosemount Avenue
New Window Frames in HTC
Old Toilet Block Demolished at Gate Lodge
Outlets on HTC
Removal of Fences and Railings in Bowling Green at Rosemount Avenue
Roof Overhead in Cafe
Spreading Sand on MUGA Carpet
Stone Pillar at Contact Sports Centre Car Park
Stripping Top Soil in New Play Area