Brooke Park

Works have been continuing in Brooke Park across all the buildings, the MUGA and the landscaped areas.  At the bottom of the Park, the gate lodge has had a dehumidifier and blow heater installed at various intervals throughout the month. The electricians and plumbers have continued to work on the horticultural training centre and the contact sports centre.  Work has also been continuing on the roof of the Café/pavilion. The rubber fill has been laid onto the MUGA and the stone mason has been busy with the boundary walls and pillars at Rosemount Avenue. The top soil has been laid out on some of the proposed new beds and the area forming the new playground and terrace has been marked out and excavated. 

Block Work & Mechanical Ventilation System in Sports Centre

 

Blow Heater in Gate Lodge

 

Completed MUGA Carpet with Sand & Rubber

 

Electrics in HTC

 

External Door Frame in Contact Sports Centre

 

Inside Proposed Cafe / Pavilion

 

Laying Terrace between Cafe and Childrens Playground

 

Middle Top Stone Steps between Pond and Cafe

 

New Stone Pillar at Rosemount Avenue

 

New Window Frames in HTC

 

Old Toilet Block Demolished at Gate Lodge

 

Outlets on HTC

 

Removal of Fences and Railings in Bowling Green at Rosemount Avenue

 

Roof Overhead in Cafe

 

Spreading Sand on MUGA Carpet

 

Stone Pillar at Contact Sports Centre Car Park

 

Stripping Top Soil in New Play Area

 

Top Soil Filling Kerb Lines